50hertz.com
EN

Sprache auswählen

  • DE
  • EN
50hertz.com
EN
  • DE
  • EN
  • Media
    Media
    • Media library
    • Contact
    • Press releases
  • Career
  • Investor Relations
  • Partners
    Partners
    • Grid customers
      Grid customers
      • Grid access
    • Balancing group customers
    • Market communication
    • System services
      System services
      • Utilisation before limitation
      • Grid losses
      • Grid reserve
    • Standard contracts
    • Suppliers
      Suppliers
      • SAP Business Network
      • Frequently Asked Questions
      • Downloads
        Downloads
        • Principles
        • Previous versions of purchasing conditions
  • Company
    Company
    • Structure
      Structure
      • Management
      • Supervisory Board
    • Roles
    • Business locations
      Business locations
      • The 50Hertz Netzquartier
    • Sustainability and Human Rights
      Sustainability and Human Rights
      • CSR Portal
      • Occupational safety
      • Engagement
      • Notices & Reports
    • Innovation
    • Partnerships
      Partnerships
      • Scientific Advisory & Project Board (SAPB)
    • Strategy
      Strategy
      • Future. Renewable
      • Future. Economic
      • Future. Digital
      • Future. Thoughtful
  • Grid
    Grid
    • Grid developement
      Grid developement
      • Onshore projects
        Onshore projects
        • SuedOstLink
        • SuedOstLink Plus
        • NordOstLink
        • 380 kV overhead line Pasewalk – Bertikow
        • 380-kV overhead line Güstrow – Parchim Süd – Perleberg
        • 380-kV overhead line Perleberg – Wolmirstedt
        • 380 kV overhead line Pulgar – Vieselbach
        • 380-kV Berlin diagonal power link
          380-kV Berlin diagonal power link
          • Videos
        • 380 kV overhead line "Nordring Berlin"
        • Third interconnector
        • Grid connection of the Jessen/Nord substation
        • Grid reinforcement of 380-kV high-voltage transmission line Röhrsdorf-Weida-Remptendorf
        • South-West Interconnector
        • Uckermark Line
        • Grid reinforcement Mecklar-Vieselbach
        • Eulenberg substation
        • Grid reinforcement Teltow-Fläming
      • Offshore projects
        Offshore projects
        • Grid connection OST-6-1
        • Hansa PowerBridge
        • Ostwind 2
        • Ostwind 3
          Ostwind 3
          • Substations onshore/offshore
        • Ostwind 4
        • LanWin3
        • Bornholm Energy Island
      • Interconnectors and phase shifters
      • Concluded projects
        Concluded projects
        • Kontek 400-KV Grid Connection
        • Ostwind 1
        • Combined Grid Solution
        • 380-kV line Bärwalde – Schmölln
        • 380 kV grid connection to the Förderstedt substation
        • Baltic 1
        • Baltic 2
        • Wind Bus Bar
      • Planning criteria
      • Planning and approval process
        Planning and approval process
        • Grid Development Plan (GDP) and Federal Requirement Plan
        • Planning and licensing
        • Transparency and public participation
      • Projects of Common Interest (PCI)
      • BESTGRID
        BESTGRID
        • 50Hertz pilot project
        • Publications
      • compactLine
    • System control
      System control
      • Grid control
      • System balancing
      • Grid availability
      • Redispatch
    • Grid operations
    • MCCS
    • MCCS DSA
    • Market sounding: State Estimator MCCS NextGen
  • Market
    Market
    • European internal energy market
    • Grid usage and congestion management
      Grid usage and congestion management
      • Usage of interconnectors
      • Usage of 50Hertz grid
      • Congestion management international
      • Congestion management national
    • Balancing energy
    • Market roles
  • Transparency
    Transparency
    • Grid Data
      Grid Data
      • Installed capacity
        Installed capacity
        • Wind power
        • Photovoltaics
      • Production & grid feed-in
        Production & grid feed-in
        • Production
        • Grid feed-in
        • Wind power
        • Photovoltaics
      • Disclosure of EEG data
        Disclosure of EEG data
        • Annual EEG bill
        • Publications on EEG balancing group
      • Congestion management
        Congestion management
        • Measures as per § 13 para. 1 EnWG (Conventional power plants)
        • Measures as per § 13 Abs. 1 EnWG (EE and VNB)
        • Measures as per § 13 para. 2 EnWG
        • Commercial transactions to balance the redispatch balancing group
        • Archive Measures as per § 13 EnWG
        • Countertrading
        • Outage and Planning
        • Trade transactions to maintain the system balance
      • Balancing
        Balancing
        • Control reserve (capacity provision)
        • Control energy (activated balance energy)
        • Archive control energy
    • Positions and Contact
  • Suppliers
  • Marketcommunication
  • Business Portal
  • Grid connection request

Sprache auswählen

  • DE
  • EN

  • Grid developement
    • Onshore projects
      • SuedOstLink
      • SuedOstLink+
      • NordOstLink
      • 380 kV overhead line Pasewalk – Bertikow
      • 380-kV overhead line Güstrow – Parchim Süd – Perleberg
      • 380-kV overhead line Perleberg – Wolmirstedt
      • 380 kV overhead line Pulgar – Vieselbach
      • 380-kV Berlin diagonal power link
      • 380 kV overhead line "Nordring Berlin"
      • Third interconnector
      • Grid connection of the Jessen/Nord substation
      • Grid reinforcement of 380-kV high-voltage transmission line Röhrsdorf-Weida-Remptendorf
      • South-West Interconnector
      • Uckermark Line
      • Grid reinforcement Mecklar-Vieselbach
      • Eulenberg substation
      • Grid reinforcement Teltow-Fläming
    • Offshore projects
    • Interconnectors and phase shifters
    • Concluded projects
    • Planning criteria
    • Planning and approval process
    • Projects of Common Interest (PCI)
    • BESTGRID
    • compactLine
  • System control
  • Grid operations
  • MCCS
  • MCCS DSA
  • Market sounding: State Estimator MCCS NextGen
Home/Grid/Grid developement/Onshore projects/Uckermark Line/Background information

Background information

The detailed plan of the planning approval procedure

With the preparation of the planning approval procedure, the real precision work began, namely to factor the different conservation interests into the line plan. Taking local interests into account, the initial line plan was adjusted in 13 places in total. In Heinersdorf, for instance, the line's route was moved to the side of the existing wind farm facing away from the town, as suggested by local residents.

The planning approval procedure aims to achieve optimised routing through participation of so-called representatives of public interests, such as nature conservation authorities. In this respect, the planning tries to find a balance between citizen's interests and those of the environment. The planning authorities (for Brandenburg, this is the State Office for Mining, Geology and Raw Materials (LBGR)) ensure that all land owners affected by the construction project are consulted and that their objections are considered and weighed.

The surveyed corridor is 500 metres wide. The future overhead line route, however, will only have an average width of about 70 metres. This allows us to minimise the damage to settlements, natural areas and the landscape.

Expansion also means revitalisation: planned compensation measures

Compensation measures are always necessary when an infrastructure project impacts the environment. If trees need to be cut for a line route, the project developer shall compensate for this elsewhere.

For the Uckermark line, 50Hertz is currently planning about 70 of such compensation measures, included in the planning approval request. Furthermore, the State Office for Mining, Geology and Raw Materials (LBGR), in its capacity of planning authority, can later impose additional obligations in the planning approval decision.

The map shows the locations and nature of these measures. There are four different types: Firstly, there are gardening and landscaping measures, such as orchards. Secondly, in case of forest conversion and reforestation, it is important to provide reasonable compensation for unavoidable changes to the forest's resources. Monoculture is often replaced by mixed forests. Thirdly, there are measures to restore nature to previously developed areas, for instance by pulling down old buildings. Fourthly, existing overhead lines are decommissioned, erasing their interference with the landscape. To compensate for the 115-kilometre Uckermark line, some 110 kilometres of an existing 220 kV line are removed. This is complemented by other measures.

Documentation: Feasibility study on underground cable solution in Eberswalde

The route of the existing 220 kV overhead line already leads to Finow-Ost and the Brandenburg quarter of Eberswalde, fairly close to the built-up area. The new Uckermark line, with a high voltage level of 380 kV, should in principle be constructed on this existing route. There are only slight deviations in both residential areas, in order to create a greater distance between the route and the Buildings.

The schematic drawing shows a cross section of the trench structure of a cable route for the western variant (variant 2). This variant had to include a 110 kV line from the distribution grid (in the middle). Without the lateral access roads and the construction area, the route is about 16 metres wide. Not pictured either are the necessary cable pits and transition structures.

After discussions with the city of Eberswalde, 50Hertz declared in 2011 that it was willing to research the conditions for an alternative realisation as an underground cable over a stretch of two kilometres. In February 2012, given the legal situation and the result of the feasibility study, 50Hertz decided to maintain the planned overhead solution. Here, 50Hertz documents the studies presented by CONSULECTRA, a consulting firm based in Düsseldorf, in April and August 2011.

Downloads

  • FEASIBILITY STUDY CABLE LINK EBERSWALDE APRIL 2011 Download PDF (805.37 KB)
  • ADDENDUM TO FEASIBILITY STUDY CABLE LINK EBERSWALDE AUGUST 2011 Download PDF (514.93 KB)

Map of Eastern variant cable link Eberswalde

  • DOWNLOAD PDF (1.47 MB - GERMAN)

Map of Western variant cable link Eberswalde

  • DOWNLOAD PDF (1.02 MB - GERMAN)

Publications

Newsletter Uckermark line edition 01/12

  • DOWNLOAD PDF (2.2 MB - GERMAN)

Flyer Uckermark line

  • DOWNLOAD PDF (1.1 MB - GERMAN)

Info letter Uckermark line 1st Edition

  • DOWNLOAD PDF (3.7 MB - GERMAN)

Info letter Uckermark Line 2nd Edition

  • DOWNLOAD PDF (3.0 MB - GERMAN)

Info letter Uckermark Line 3rd edition

  • DOWNLOAD PDF (3.4 MB - GERMAN)

Info letter Uckermark Line 4th edition

  • DOWNLOAD PDF (3.0 MB - GERMAN)

Info letter Uckermark Line 5th edition

  • DOWNLOAD PDF (4.5 MB - GERMAN)

Info letter Uckermark Line 6th edition

  • DOWNLOAD PDF (6.9 MB - GERMAN)
CONTACT

Dr. Dirk Manthey

Public participation
  • Tel:
    +49 (0) 30 5150-3419
  • E-Mail:
    dirk.manthey@50hertz.com
  • Contact
  • Imprint
  • Data protection
  • Newsletter
  • Sitemap
  • per E-Mail teilen auf Facebook teilen auf X teilen
Login